Size: 6 stories
GC: Siena Construction
Electrical Crew: 25
Scope: Retrofit lighting throughout occupied law school facility, replacing and re-lamping more than 3,000 existing light fixtures with energy efficient LED fixtures and lamps.
Highlights:
- Lighting retrofit provided in compressed, three-week schedule during winter break
- Much of lighting retrofit project performed on lifts over library stacks and desks
- Performed work in occupied law school building with minimal disruption to daily university operations
- Energy project achieved significant reduction in building’s wattage consumption
- Close coordination with general contractor, Siena Construction and architect, STA Design to meet fast-track project requirements
- Project timeline: 3 weeks