125 Summer St. – Lobby, Boston MA

By December 6, 2016September 8th, 2021Commercial

Size: 8,000 sq/ft
GC: Turner Construction
Electrical Crew: 8 at peak

Scope: Modifications of first floor to create a new entrance to building.  New lobby was constructed with decorative LED lights, enhanced security desk, sleek new turnstiles, restrooms and an AV wall.  During the two-phase construction project, J&M Brown demoed old restaurant spaces, installed new distribution panels, and coordinated hundreds of feet of conduit runs in garage.  Additionally, J&M Brown’s low-voltage division, SpectrumIT, performed the security scope for this project.

Highlights

  • High-end fixture package with remote drivers
  • Utilized Lutron lighting control panels, switches and photocells
  • Plaza light poles and uplights
  • Timeline: 9 months