Brockton Hospital – Electrical Infrastrucutre

By February 16, 2024Healthcare

Owner: Signature Healthcare
Electrical Peak at Crew: 51

A devastating 10-alarm fire shut down this hospital putting the healthcare needs of the community in jeopardy.  J&M Brown was called in to help design-assist a new electrical infrastructure that would get the hospital back up and running.  New switchboards and distribution panels were expediated, while all new feeders and branch wiring were run to replace the damaged equipment.  While shutdown, the hospital was able to also renovate the Lobby, Emergency Room, Outpatient Surgical Care and other areas to provide a better experience for their patients.

 

Project Highlights:

  • 18 month timeline
  • Carport solar panel arrays
  • New incoming service being back-fed from solar arrays