Four Seasons Hotel Boston

4_seasonsSize: Renovation to 114 guest bathrooms
Owner: Four Seasons Hotels
Electrical Crew: 5 electricians and technicians

Scope: Electrical and telecom renovations to majority of hotels guest bathrooms – 114 in total – in luxury hotel. J&M Brown also provided original core and shell electrical construction of Four Seasons Hotel and Residences in mid-1980s.

Highlights:

  • All bathroom installations provided in occupied hotel
  • Construction plan included closing off individual floors while construction was ongoing on that floor.
  • J&M Brown teamed with Spectrum IT in the installation and testing telephones in all guest bathrooms
  • Project timeline: 5 months

Unique Project Challenge: Work provided in occupied hotel without disruption to guests