
Global investment firm, Cambridge Associates, moved its headquarters into Winthrop Center this past summer.
Global investment firm, Cambridge Associates, moved its headquarters into Winthrop Center this past summer.
J&M Brown was the electrical contractor for this fast-track project covering four floors for GMO’s new office in downtown Boston.
J&M Brown continues to do work at the old Boston Globe building on Morrissey Blvd. After completing the gut and renovation of the sprawling building,
J&M Brown was recently awarded as the Electrical Contractor for Eaton Vance/Morgan Stanley’s new office space at the newly renovated One Post Office Square building in downtown Boston.
J&M Brown was the electrical contractor for Foley Hoag’s office space
J&M Brown was the electrical contractor for Foley Hoag’s office space
J&M Brown was delighted to be the electrical contractor for Google’s office fit-out at 150 Broadway in Kendall Square.
Capital One moves into Kendall Square with a 3-floor fitout
Construction of 321 Harrison is underway. J&M Brown has begun the core & shell coordination for this new 232,000 office building in Boston, MA.
J&M Brown Company completed the 250,000 square-foot, 10-floor fit-out of Putnam Investments new headquarters at 100 Federal Street in the heart of Boston’s financial district.
The scope entailed comprehensive electrical distribution and lighting installations for the offices which house approximately 1,000 Putnam staff members. The project scope included eight floors of state-of-the-art offices, a 150-plus seat auditorium, conference centers, a network of meeting rooms, a new data center, a commercial kitchen, and a mezzanine roof deck.
Data center and electrical distribution installations included two UPS systems, three standby electrical risers and internal communications risers that are tied to the standby emergency generator. Six automatic transfer switches that tie into the generator were also installed.
The project team was headed by JMB Vice President and Project Manager Dennis Nigro and Foremen Bill Marchant, Dave Marchand, and Mike Sawyer.
Putnam moved from into its new 100 Federal headquarters from its former offices at One Post Office Square in October 2018.
Project Challenges
Coordination of multiple power shutdowns during the project to meet building owner and tenant requirements and also to ensure critical data was maintained throughout the project.
JMB met the fast-track, nine-month project schedule managing a crew of 50 IBEW Local 103 electricians at peak construction. To meet Putnam’s move-in schedule, the power distribution scope was completed in four months and 8 floors of elaborate office fit-out requirements were completed in only seven months.
###